Agile Delivery in SAP Projects
Course quiz
Agile Delivery in SAP Projects
Keep this: job aid
Agile SAP delivery card
- Hybrid: phases and gates outside, two- to four-week sprints inside Realize.
- Scaled Scrum: one backlog, one definition of done, one sprint calendar, Scrum of Scrums.
- Stories: specific role, want, benefit; fit one sprint; INVEST.
- Rank with MoSCoW plus strict order; do high-value, high-risk items early.
- Definition of ready includes acceptance criteria and known dependencies.
- Plan 50 to 70 percent of hours; tasks of four ideal hours or less; fixed sprint scope.
- Done = linked test cases, passed run with evidence, role-based test user, product owner acceptance.
- Done is not Shippable: SIT and final acceptance on migrated data close Realize.
- Report burn-up, velocity and requirement traceability together; count only Done.