Cost Object Controlling: WIP, Variances and Settlement
Course quiz
Cost Object Controlling: WIP, Variances and Settlement
Keep this: job aid
Production order period-end checklist
- Sequence: overhead → WIP → variances → settlement. Read each log before the next step.
- Open orders (REL, PDLV): balance = WIP at actual cost. Finished (DLV, TECO): balance = variance.
- WIP needs a results analysis key; calculation stores it, settlement posts it to FI.
- WIP posting: debit unfinished goods inventory, credit change in WIP; reversed when the order finishes.
- Target cost version 0 = total variance (settled). Versions 1-3 are analysis only.
- Categories: input price, input quantity, resource-usage, remaining input, lot size, output price, mixed-price, remaining, scrap.
- No variance key, no variances. Check it on orders with obvious overruns.
- Variance posting: debit price differences, credit finished goods inventory change; split by category if configured.
- Evidence: zero balance on settled finished orders; G/L WIP account = WIP list; price differences = settled variances.